A walkthrough of the Arundel project and how the challenges it presented were overcome

 

Second floor - Underground

We took the boilers through the underground parking area down to the level below, where the boilers were to be installed.

 

The boilers had to be on skates to enable movement. The clearance underneath the concrete roof beams was a few centimetres.

Of course the roof beams cannot be moved or altered in any way.

 

By a combination of hard work and extreme care all boilers were safely transported to the boiler room

More >>

   

 

Another Level

Click for large image

To access the boiler room meant we had to remove a section of the internal wall.

 

The room itself was about a metre lower than the underground car park level. We used steel beams to bring the boiler into the room and then lowered it to the floor level.

All lifting had to be manual as the roof clearance meant that mechanical aids could not be used.

More >>

 

     
     
installed
Click for large image

In total we moved and installed six boilers.

It was a labour intensive operation but there was no alternative.

 

Mechanical lifting aids would be unable to get underneath the boiler to lift it and there was no room - it was only after careful measurement that MRI London could confirm it was possible to get under the roof beams.

 

Although possible the job still required care and attention to ensure completion.

 

This is a difficult operation as it moves the weight to one end which causes instability.

More>>

   

 

People Do What machines Can't
Click for large image

Each boiler was taken to the 2nd lower floor

The job couldn't be rushed but it had to done swiftly, if the floor was uneven at any point the boiler would hit the roof beams.

If the roof and boiler made contact we don't know which would have come off worse and thankfully we never found out.Our main concern was ensuring the boiler didn't get trapped under the beam and we had to divert to avoid pipe-work and cabling.

   
     
No Headroom
Click for large image

The only thing harder than getting a weighty boiler to move is getting it to stop.

 

Before we attempted to go underneath the roof beam we had to ensure it could get under.

 

As we moved it needed constant attention to keep the speed smooth and constant, the direction straight and one eye on the clearance - there was no room for error.

   
     
Hard Work & Team Work
Click for large image

There are times when all the sophisticated tools at our disposal simply can't do the job.

Physically hauling heavy plant is very strenuous work, but in this case there was no alternative and it had to be done somehow.

 

Our teams are used to hard work and working hard as a team, there's no room for slackers at MRI London.

 

"If that's what it takes then that's what we will do" is our attitude.

   
     
A Wall In The Way? Take It Out!
Click for larger image

At the end of the long haul was a wall. There was no other way to access the boiler room so we took the wall away.

 

As the floor was about a metre lower we had to bring the entire boiler into the room and then lower it.

 

This is an extremely hazardous operation. MRI London had the confidence to do it because we've done it before and know what to do.

   
     
Rigging

Click for large image

Bearing in mind that we cannot lift the boiler very high getting the lifting chains underneath and in the right place wasn't as simple as it sounds.

 

As all team members knew what had to done and how it should be done the operation went very well.

 

The main problem is the tendency for the boiler to drop at an angle once it's just over halfway over the ledge.Getting the chains in the right place was essential, once the weight is taken up there is no way to reposition them.

     
     
Forwards and Down 

Click for large image

Each boiler was carefully lined up straight and kept level.

 

Side swing would result if when lifted one side was lower than the other - which is extremely dangerous for all involved, it's very hard to stop once it's going.

 

If the boiler drops downwards it is possible for it to slide forwards and out of the chain cradle - again once it starts there is very little you can do.

 

So proper planning at the outset is essential because you can't do anything about it later - it's too late.

   
     
All In Safely
CLick for large image

Limited Room

 

We couldn't bring the boiler in as far as we would have liked because the building structure was in the way.

 

Careful preparation beforehand meant that we were in the only place it was possible to bring the boiler sufficiently in to lower it to the ground.

 

We would have preferred more room to manoeuvre but we didn't have it.

 

We had to take care to not knock our lifting beam support - something easy to do that would mean disastrous results.

 

 

     
All In And Drop
Click for large image

Our team had to keep the guy cables taut to stop any swinging about in any direction.

Particularly when the lifting stops and starts the boiler keeps going of its own accord, we allow for this as we move but also ensure all of the team are alert, vigilant and ready to respond.

 

To do the job well it takes a good team who know their job - that's MRI London.

     
 
Installed
Click for larger image

The boilers were placed on their foundations and made secure.The section of wall we removed for access was replaced and made good.

 

MRI London often find the size of the hole and the size of the heavy plant are about the same - and there is nothing you can do about either.

 

If it is possible MRI London will do it - if it's not possible... we've done that before and we'll find a way to do it again.

     
 
 
 

MRI London Wharf Road, Denton Industrial Estate, Gravesend, Kent DA12 2RU   Tel: 01474-354500   Fax: 01474-354600

MRI London is a Division of Rollmark Engineering Limited Registered Company: 03460248

© 2010 Rollmark Engineering Ltd A| Photography By Spikesfotos | Web Design, Maintenance & Management by Xenon