Victoria - Part 2 of 3


Road Closure
Click for large image

Part Closure

At Victoria the lift was from the main road, we were ale to close only part of the road and allow traffic through.

Pedestrians were diverted to the opposite pavement during the lift.

All deliveries were under a strict timetable, as one left the next was quickly brought up and took it's place.

Proper planning prevents poor performance.


Room to Work

The area we closed was to accommodate the crane and the lorry bringing in the load.

As always we had to work within tight schedules, all went according to the plan and the lift was a complete success.

All units were quickly in place with the minimum inconvenience for everyone.

Click for large image


Click for large image

In and Out

When closing the section of road we had to ensure that the low-loader, with the Air Handling Units, could line up with the crane.

The low-loader had to get in place without stopping the traffic.

MRI London's experience means we predict accurately all that is needed. We know the limitations of the crane and where the low-loader must be.

We know the best way for the low-loader to" get in and get out".